Monday, March 21, 2011

Roof Prefabrication Phase I

In order to facilitate the easier movement of the trusses in and out of the high-base space after construction, we built dollies. They also helped us to construct a guide for a fixed distance between the dollies on each side.



Once the distance between the two trusses was established, each truss's location was measured and each truss was nailed to the appropriate guide. We then began framing between the two trusses.


Thursday, March 17, 2011

Pre-Construction Phase I

This week, design/build lab moved all of our operations to our off-campus facility where prefabrication will occur. On Monday we discussed logistics and began working towards getting our salvaged materials ready for construction.


We've been working with the wood harvested from the Tire Warehouse in Clifton Forge to cut the timbers down to size for our design.
Because the wood is being reused, there were some nails left over from the original construction. The nails all had to be removed, and the ends of each piece of wood were cut to be square.
The oak seen in these photos will be reused as framing lumber for the building of the market, which includes a restroom, storage facility, and an office for the Market Manager.

Tuesday, March 1, 2011

Site Preparation Begins

Yesterday preparation of the future site of the Covington Farmer’s Market began with the removal of the asphalt.

The design for the site calls for a market floor and a green park space to cover most of the existing site. However, to facilitate the unloading and setting up of market stalls, as well as parking, the asphalt on the boundary of the lot opposite of Monroe St will be repaved. Some of the asphalt currently being removed from the existing parking lot will be recycled to make the new parking spaces.





Virginian Review, Saturday February 26th


The Covington Farmer's Market made front page news in the Virginian Review on Saturday. Information on the site preparation was announced to begin on Monday, the 28th of February. The article also explained a bit about the steps taken in the design process and the deconstruction of the tire warehouse in Clifton Forge as well as the repurposing of the tire warehouse's wood.

Friday, February 18, 2011

Public Presentation in Covington






On Wednesday night, design/build lab presented our ideas and designs to the farmers and members of Olde Town Covington, as well as to some of the volunteers for the project.

We also explained the process we will be using to construct. We will be prefabricating the structure of the building, roof, and market floor off-site in a location in Blacksburg. Simultaneously, the ground and foundations for the market space will be prepared in Covington. Once the ground and foundations are ready, the modular pieces constructed in our Blacksburg facility will be transported up to Covington for assembly on-site.

The presentation lead to friendly conversation with those who attended because of the enthusiasm from the farmers and Olde Town Covington.


Sunday, February 13, 2011

City Council Meeting, February 8th



On Tuesday, February 8th, Covington City Council approved the site plan for the Covington Farmer's Market. Design/build lab can now begin construction by prefabricating off-site in Blacksburg.


Wednesday, February 2, 2011

Market Proposal: Translucence





A translucent membrane reflects the delicate curve and allows for the passage of light while functioning as a protective skin. Rectilinear members create the experience of a curved surface.