Saturday, May 14, 2011
Ground Prefabrication Phase III
Friday, May 13, 2011
Site Preparation Phase III
On Thursday, May 12th, the steel columns were delivered and installed on site in Covington. These steel columns will support the roof sections over the market portion of the site. Our on-site contractor worked to get the columns assembled and installed as soon as possible, so that it would not delay the progress of the rest of the project.
A view from the market manager's office to the site, before and after column installation.
A view from the market manager's office to the site, before and after column installation.Tuesday, May 10, 2011
Ground Prefabrication Phase II
In order to line up the decking pieces, finishing nails were used as spacers between rows of locust to keep consistent spacing throughout. Some of the wood was bowed or warped, so we had to use bow wrenches, ratchet straps, or clamps to line the pieces up properly.
Once the wood was aligned, we had to pre-drill holes in the locust to prepare for screws. Since locust wood is so dense, it was too difficult to screw directly into the wood without any preparation or guidance.
We used a screw gun to insert the screws into each decking piece. The screws attach the market floor to the joists beneath.Building Prefabrication Phase III
A view from Monroe St. of two of the building sections after being installed on site. All three buildings are on site and ready for the finalizing of interior details.
Friday, May 6, 2011
Roof Prefabrication Phase III
JENFAB, Inc. came to our Blacksburg facility Tuesday and Wednesday to begin loading, transporting, and unloading completed prefabricated sections of the market roof up to Covington.
Because many of the roof sections were parked throughout the site, we had to move and prepare the sections for departure before they could be moved. Once they were relocated to an appropriate site for the forklift to be able to lift and maneuver each truss section onto the flatbed truck. Straps were pulled through the trusses and used to lift the section up for its movement.
Once each section was lifted, we had to guide it to a space where the truck would back up for loading purposes. Because of the many buildings in the area, much caution was used in the movement and guidance of the prefabricated pieces.
Friday, April 29, 2011
Building Prefabrication Phase II
With the application of the tar paper on the building finalized, battons were then mounted to the building so that cladding could be added to the exterior.
Using the battons on two walls of each building, the cladding was mounted to the necessary sides using a drill, a screw gun, and when needed, a clamp or ratchet strap. The screws were screwed into each batton to ensure a sturdy exterior rain screen for the building sections. The design for the buildings was to have the wood cladding wrap up and around the entire exterior in one direction so that continuity of the ground plane's direction was maintained. The seams on the buildings will align with the seams in the deck on site.
Once cladding was applied to all of the appropriate walls, any excess was trimmed to create a smooth seam between roof and wall.
Monday, April 25, 2011
Roof Prefabrication Phase II