Friday, May 6, 2011
Roof Prefabrication Phase III
JENFAB, Inc. came to our Blacksburg facility Tuesday and Wednesday to begin loading, transporting, and unloading completed prefabricated sections of the market roof up to Covington.
Because many of the roof sections were parked throughout the site, we had to move and prepare the sections for departure before they could be moved. Once they were relocated to an appropriate site for the forklift to be able to lift and maneuver each truss section onto the flatbed truck. Straps were pulled through the trusses and used to lift the section up for its movement.
Once each section was lifted, we had to guide it to a space where the truck would back up for loading purposes. Because of the many buildings in the area, much caution was used in the movement and guidance of the prefabricated pieces.
Friday, April 29, 2011
Building Prefabrication Phase II
With the application of the tar paper on the building finalized, battons were then mounted to the building so that cladding could be added to the exterior.
Using the battons on two walls of each building, the cladding was mounted to the necessary sides using a drill, a screw gun, and when needed, a clamp or ratchet strap. The screws were screwed into each batton to ensure a sturdy exterior rain screen for the building sections. The design for the buildings was to have the wood cladding wrap up and around the entire exterior in one direction so that continuity of the ground plane's direction was maintained. The seams on the buildings will align with the seams in the deck on site.
Once cladding was applied to all of the appropriate walls, any excess was trimmed to create a smooth seam between roof and wall.
Monday, April 25, 2011
Roof Prefabrication Phase II
Saturday, March 26, 2011
Building Prefabrication Phase I
Thursday, March 24, 2011
Site Preparation Phase II
This week the ground began to be prepared for the concrete foundations on site. These pictures, taken Wednesday March 23rd, show the ground excavations for placement, as well as the arrangement of rebar used to strengthen the foundations.

Although they will not be seen in the final product, the foundations are crucial to the construction of the market. They will be used to support the market floor, building and roof.
Wednesday, March 23, 2011
Ground Prefabrication Phase I
The final product, one market floor frame. These will be used to support the market floor made of locally grown locust wood.
Monday, March 21, 2011
Roof Prefabrication Phase I
Once the distance between the two trusses was established, each truss's location was measured and each truss was nailed to the appropriate guide. We then began framing between the two trusses.