Friday, May 6, 2011

Roof Prefabrication Phase III

JENFAB, Inc. came to our Blacksburg facility Tuesday and Wednesday to begin loading, transporting, and unloading completed prefabricated sections of the market roof up to Covington.



Because many of the roof sections were parked throughout the site, we had to move and prepare the sections for departure before they could be moved. Once they were relocated to an appropriate site for the forklift to be able to lift and maneuver each truss section onto the flatbed truck. Straps were pulled through the trusses and used to lift the section up for its movement.



Once each section was lifted, we had to guide it to a space where the truck would back up for loading purposes. Because of the many buildings in the area, much caution was used in the movement and guidance of the prefabricated pieces.




The section was then lowered onto the flat bed, where we used blocks to accommodate the unique angles of each piece.



Sections were then separated from the fork lift and strapped down to the bed to secure the pieces for limited movement in preparation for the trip up I-81 to Covington.



Due to the size of the load, as well as regulations for highways, appropriate safety precautions were taken and signage was used to make drivers aware of the larger size of the truck's cargo. Two trusses were able to be sent up at a time on the truck.



Friday, April 29, 2011

Building Prefabrication Phase II

The first step after constructing and erecting the three building sections was to apply the plywood to the building. Once the buildings were square and level, the plywood helped us to maintain the square status of the building, while creating an interior and exterior space to each individual room.After the plywood was put on the building, we added tar paper to the exterior in order to help us keep water off and out of the building. Although tar paper is not water tight, it is water resistant and was very helpful in preparing each building for its final exterior material.






With the application of the tar paper on the building finalized, battons were then mounted to the building so that cladding could be added to the exterior.






Using the battons on two walls of each building, the cladding was mounted to the necessary sides using a drill, a screw gun, and when needed, a clamp or ratchet strap. The screws were screwed into each batton to ensure a sturdy exterior rain screen for the building sections. The design for the buildings was to have the wood cladding wrap up and around the entire exterior in one direction so that continuity of the ground plane's direction was maintained. The seams on the buildings will align with the seams in the deck on site.



Once cladding was applied to all of the appropriate walls, any excess was trimmed to create a smooth seam between roof and wall.

Monday, April 25, 2011

Roof Prefabrication Phase II

Joists were placed between each of the trusses that makes up each section. Once all of the josts for the entire truss were framed out, we added battons to the top of the roof section. These battons will be used to add the metal roofing to the structure once the roof sections are placed together on site.



Thanks to the high base space's pully system, we were able to separate and lift the roof sections off of their original supports once completed. Each roof section is approximately 2,700 pounds.


In order to begin working on the ceiling of each roof section, we had to use the pully system to lift and rotate each roof section upside down.


Tar paper was then added to the roof sections to prevent moisture from accumulating inside the section. We used a combination of white pine and repurposed heart pine salvaged from the Tire Warehouse in Clifton Forge to create the market ceiling.


The last step of the process is to apply waterproofing so that the wood would not get wet. Once each roof section was finished we were able to use the same pully system to lower the section onto dollies to move the sections out of the work space. The whole class would then work together to move the trusses out to locations where they could be "parked" until transportation up to Covington.

Saturday, March 26, 2011

Building Prefabrication Phase I

After reusing much of the oak from the Tire Warehouse to make 2x4s, we learned how to lay out walls for building construction, and used the oak as the wall studs.
Using a nail gun, we constructed all of the walls for the bathroom section of the building.

Once each bathroom wall was constructed, we raised them and squared them off to make sure each one was fitting perfectly at 90 degree angles. We braced the building afterwards to maintain the square overnight until we could continue working on the building.

Thursday, March 24, 2011

Site Preparation Phase II

This week the ground began to be prepared for the concrete foundations on site. These pictures, taken Wednesday March 23rd, show the ground excavations for placement, as well as the arrangement of rebar used to strengthen the foundations.


Although they will not be seen in the final product, the foundations are crucial to the construction of the market. They will be used to support the market floor, building and roof.

Wednesday, March 23, 2011

Ground Prefabrication Phase I

When the pressure-treated lumber arrived last week, we began to measure and cut pieces of wood to the sizes we needed for the frames for the market ground.
After they were cut, we began to layout the sections of wood we had cut and mark 90 degree angles so that the framing construction would be square.

Once the pieces were lined up, we held them in place as a nail gun was used to connect each joist to the girder on the exterior.

The final product, one market floor frame. These will be used to support the market floor made of locally grown locust wood.

Monday, March 21, 2011

Roof Prefabrication Phase I

In order to facilitate the easier movement of the trusses in and out of the high-base space after construction, we built dollies. They also helped us to construct a guide for a fixed distance between the dollies on each side.



Once the distance between the two trusses was established, each truss's location was measured and each truss was nailed to the appropriate guide. We then began framing between the two trusses.