Tuesday, November 23, 2010
Tire Warehouse Deconstruction, 11.15.10
Last M
onday, November 15th, design/build lab began
its final phase of deconstruction on the tire warehouse.
We began to take apart pieces that were not necessary to the structure's integrity.
We removed the last bit of metal siding from the end of the warehouse to expose the wood structure of the building completely.
Clean up on the site began as pieces of tar paper that were removed from the roof were collected and moved to the dumpster.
By Monday's end, the wood boards from the roof had been completely removed, exposing the trusses of the structure.