On Friday, May 13th, the decking sections for the market floor began to be moved from our prefabrication facility to the site of the Covington market.

Once the groups of sections were lifted from their original stacks, we had to guide them out to the loading area while the forklift carried the sections out.

Sections were carried and loaded three at a time. Straps were wrapped around the width of the section to hoist them into the air as they were guided onto the truck bed.

We were able to load twelve ground sections onto the truck. The twelve sections will make up six of the fifteen ten foot by approximately 30 foot sections used to make the market floor. An additional load of frames and deck sections were transported on Saturday.