Thursday, May 26, 2011

Market Ceiling and Lights


In order to transport and install all the roof sections in Covington without breaking the edge boards of the ceiling, the end pieces of the ceilings were removed for installation. This left space between each two roof sections where we needed to repair tar paper ripped in transport, as well as insert and secure the edges of the ceiling.




Blocking had to be made and inserted between the roof sections to allow for mounting the LED lights for the market, which were generously donated by Traxon Technologies.




After the blocking was inserted the ceiling piece for the edges of the sections were reinstalled. As a final touch, the lights for the market were installed in between the sections to allow for adequate lighting at night, as well as a great visual.






The final product is a sleek, finalized ceiling.

No comments:

Post a Comment